🚀 Phase 4 · v1.1 Post-Production · 5 Apr - 27 Jun 2027 · 4 Sprints
← Hub ← Production Live PHASE 4 · v1.1 12 minggu

Phase 4 · v1.1 Post-Production · Scale + Deepen

Production stable. 30-day review done. Now: deepen what's already built, add the wearables module that pilot patients kept asking for, automate onboarding so the team scales horizontally, launch telehealth as the natural extension of M4 ambient SOAP. From 5-6 tenants to 10 by Q2-end.

1. 🎯 Phase Summary

PhasePhase 4 · v1.1 Post-Production
Duration5 Apr - 27 Jun 2027 (12 weeks · 4 sprints × 3 weeks)
GoalDeepen production modules with real-world data · ship M10 Wearables · self-service onboarding · M4+ Telehealth · scale 5-6 tenants → 10
Capacity6.0 FTE (2 BE + 1 FE + 1 prompt + 1 DevOps + 1 Onboarding) + 0.5 Founder + 0.5 Doc Zam
Velocity target~75 SP/sprint × 4 = 300 SP total
Blocked byQ6 cert · 30-day production stability watch passed
Blocksv1.2 (Q3 2027 · multi-state expansion)
Phase exit date27 Jun 2027 · v1.1 retro · 10 tenants live
Sprint length change: 2-week sprints (build phase) → 3-week sprints (sustain phase). Reason: production support eats ~25% of capacity; longer sprints reduce ceremony overhead.

2. 🎨 v1.1 Themes

  • Theme 1 · Listen to data: Pilot + production gave us 4 months of usage data. Where do doctors override? Which triages go wrong? Which Rx flags miss? Sprint 4.1 closes those loops.
  • Theme 2 · Add what patients asked for: Top patient request from pilot NPS surveys: "Can you read my BP cuff?" "My CGM?" Sprint 4.2 ships M10 Wearables.
  • Theme 3 · Stop being the bottleneck: Onboarding takes 10 days because we're hands-on. Sprint 4.3 ships self-service onboarding wizard · target: 2-day cycle.
  • Theme 4 · Extend the moat: Doctors love M4 ambient SOAP. Telehealth needs the same. Sprint 4.4 ships M4+ video consultation.

3. 🏃 Sprint Catalog

4. 📅 12-Week Timeline

Week  Date              Activity
W1    5-11 Apr          Sprint 4.1 kickoff · M1 production-data audit
W2    12-18 Apr         Sprint 4.1 mid · CPG corpus expansion
W3    19-25 Apr         Sprint 4.1 demo · 4.2 prep
W4    26 Apr-2 May      Sprint 4.2 kickoff · M10 schema · vendor APIs
W5    3-9 May           Sprint 4.2 mid · BP cuff + CGM working
W6    10-16 May         Sprint 4.2 demo · 4.3 prep
W7    17-23 May         Sprint 4.3 kickoff · onboarding wizard MVP
W8    24-30 May         Sprint 4.3 mid · auto-provisioning live
W9    31 May-6 Jun      Sprint 4.3 demo · 4.4 prep · 7th tenant onboarded via wizard
W10   7-13 Jun          Sprint 4.4 kickoff · WebRTC base · video stream → Whisper
W11   14-20 Jun         Sprint 4.4 mid · ambient SOAP on video verified
W12   21-27 Jun         Sprint 4.4 demo · v1.1 phase retro · 10 tenants live

5. 🎯 Priority Matrix

ItemPatient impactDoctor impactScale unlockVerdict
M1+M4 deepening (4.1)HIGHHIGHMED✅ Ship first · production debt
M10 Wearables (4.2)HIGHMEDMED✅ Patient-requested · differentiator
Self-service onboard (4.3)HIGH✅ Required for 10+ tenants
Telehealth M4+ (4.4)HIGHHIGHHIGH✅ Moat extension · defer no further
MyKad integrationLOWLOWMED⏸️ Defer to v1.2 · KKM partnership dependency
BCN/Tamil PAMEDHIGH⏸️ Defer to v1.2 · prompt eng resource constrained
DICOM viewer expansionHIGHLOW⏸️ Defer to v1.2 · radiologist clinic onboarding first
Care plan module M11HIGHMEDMED⏸️ Defer to v1.2 · chronic care ICD bundle needed first

6. 👥 Team Capacity (steady-state v1.1)

RoleAllocationNote
Eng Lead / BE1.0 FTE~25% production support · 75% v1.1
BE Dev 21.0 FTESame split
FE Dev1.0 FTEUX iterations + new module UIs
Prompt Eng1.0 FTE4.1 corpus · 4.4 video prompt tuning
DevOps1.0 FTEWearables infra · WebRTC TURN servers · scale tuning
Onboarding Lead1.0 FTE4.3 wizard owner · existing cohort support
Founder0.5 FTEBD · scale partnerships · phase retro
Doc Zam0.5 FTEClinical sign-off · advisory · case panel review

7. 📈 Success Metrics

10
Tenants by 27 Jun
≤2 days
Self-service onboarding
≥95%
Triage accuracy (up from 90%)
≥30%
Patients with wearable linked
≥10/wk
Telehealth consultations
99.7%
Uptime (up from 99.5%)
MetricBaseline (production)Target end of v1.1
Tenants live5-610
Onboarding cycle10 days≤ 2 days (self-service)
Triage accuracy90%≥ 95%
SOAP override rate12%≤ 8%
Patients with wearables0%≥ 30%
Telehealth weekly volume0≥ 10
Production uptime99.5%99.7%
NPS (patients)52≥ 60

8. ✅ Phase Exit Criteria (27 Jun)

  • All 4 sprints (4.1-4.4) demoed and signed off
  • 10 tenants live on production · stable for 7+ days each
  • Self-service onboarding cycle proven on tenant 8, 9, 10
  • M10 Wearables: 30%+ patients linked at least one device
  • Telehealth: 10+ video consultations completed clinically · sign-off rate ≥ 95%
  • v1.1 retro complete · learnings documented
  • v1.2 plan drafted · prioritisation locked
  • Updated pen-test light review · no regressions
  • Doc Zam clinical sign-off on v1.1 entirety

9. 🔭 Beyond v1.1 (Q3-Q4 2027)

  • v1.2 (Q3): M11 Care Plans (chronic) · BCN/Tamil patient PA · MyKad NRIC integration · DICOM expansion · 20-tenant target
  • v1.3 (Q4): Multi-state expansion (Penang · Kuching · KK pilot) · second Hi-End server (load shed) · MOH partnership exploration · 40-tenant target
  • v2.0 (2028): Specialty modules (paeds-deep · OG-deep · cardio-deep) · API marketplace · partner channel (insurance · pharma) · 100+ tenant target