📅 Gantt Timeline · Sprint Plan · Critical Path · MediEco · 26 April 2026
← Hub GANTT TIMELINE 26 Apr 2026 → Mar 2027 ~11 bulan ke production

Sprint Timeline & Critical Path

Sprint-level visibility · 4 phases · 14 milestones · sprint dependencies · resource allocation · critical path. From Doc Zam approval ke production-ready.

1. 📌 Timeline Overview

Phase 0 · NOW
2 minggu
26 Apr - 10 May
Phase 1 MVP
6 minggu · 3 sprints
11 May - 21 Jun
Phase 2 Pilot
3 bulan
22 Jun - 30 Sep
Phase 3 Scale
6 bulan
Oct 26 - Mar 27

Sprint length: 2 minggu (Sun-Sat). Sprint cadence: planning Day 0 · async daily standup · review/demo Day 13 (Fri AM) · retro Day 13 (Fri PM). Doc Zam attend reviews bi-weekly, intensive Day 13 of each MVP sprint.

2. 📊 Gantt Chart (text-rendered)

11 bulan timeline · weeks W1-W48 (April 2026 → March 2027). Baca: bar position = duration. ◆ = milestone marker.

             W1   W2   W3   W4   W5   W6   W7   W8   W9   W10  W11  W12  W13  W14  W15  W16  W17  W18
             Apr/May            May/Jun            Jun/Jul            Jul/Aug            Aug/Sep
─────────────────────────────────────────────────────────────────────────────────────────────────────────
P0 Found.    [████]                                                                           ◆ Q1 Gate
Sprint 1.1        [████]                                                                       ◆ M9
Sprint 1.2             [████]                                                                  ◆ M1
Sprint 1.3                  [████]                                                             ◆ MVP done
            ◆ Q2/Q3 Gate
Sprint 2.1                       [██]                                                          ◆ M2+M5
Sprint 2.2                          [████]                                                     ◆ M7
Pilot prep                              [██]                                                   ◆ Klinik live
Pilot run                                  [████████]                                          ◆ 30-day mark
Iteration                                            [████]                                    ◆ Q4/Q5 Gate

             W19  W20  W21  W22  W23  W24  W25  W26  W27  W28  W29  W30  W31  W32  W33  W34  W35  W36
             Sep/Oct            Oct/Nov            Nov/Dec            Dec/Jan            Jan/Feb (2027)
─────────────────────────────────────────────────────────────────────────────────────────────────────────
Sprint 3.1   [████]                                                                            ◆ M3
Sprint 3.2        [████]                                                                       ◆ M6
Sprint 3.3             [████]                                                                  ◆ M8
Onboard 3K        [████]                                                                       ◆ 3 klinik
Onboard 5K             [████]                                                                  ◆ 5 klinik
Onboard 10K                 [████]                                                             ◆ 10 klinik
Hi-End upgrade                   [████]                                                        ◆ H100 deployed
MOH audit prep                        [████████]                                               ◆ Q6 final cert

             W37  W38  W39  W40  W41  W42  W43  W44  W45  W46  W47  W48
             Feb/Mar                                                Apr 2027
─────────────────────────────────────────────────────
MOH audit    [████]                                  ◆ Production cert
Steady state      [████████████]
─────────────────────────────────────────────────────

LEGEND:
[████]  = sprint duration
◆       = milestone marker
P0/P1/P2/P3 = phase boundary
P0 Foundation: blueprint LIVE · repo init · Q1 gate
P1 MVP: M9 → M1 → M4 · 6 weeks · Q2/Q3 gates
P2 Pilot: + M2/M5/M7 · 30-day pilot · Q4/Q5

3. 🏃 Sprint-by-Sprint Detail

SprintDatesGoalModulesCapacity (FTE)Gate
P0 Foundation26 Apr - 10 MayBlueprint LIVE · repo · CI/CD scaffold · klinik onboarding1.5Q1 Preflight
1.111 May - 24 MayM9 audit foundation · auth/RBAC · 11-section Patient modelM94 (3 BE + 1 FE)
1.225 May - 7 JunM1 Patient PA · symptom intake · 3-warna triage · PWA shellM14 (2 BE + 1 FE + 1 prompt)
1.38 Jun - 21 JunM4 Doctor PA · 6-tab UI · ambient SOAP · CDSS · sign-offM44 (2 BE + 1 FE + 1 prompt)Q2 internal · Q3 clinical
2.15 Jul - 18 JulM2 Pre-Consult Briefing + M5 Pharmacy PAM2 + M55 (3 BE + 1 FE + 1 prompt)
2.219 Jul - 1 AugM7 Admin PA · queue · billing · panel claim · e-InvoiceM75 (3 BE + 1 FE + 1 integration)
Pilot prep2 Aug - 15 AugKlinik onboarding · staff training · UAT · soft launch3 + Doc Zam
Pilot run16 Aug - 29 Aug2-week observed pilot dgn intensive monitoringAll P1+P2 modules2 (support) + 3 (iterate)
Pilot extended30 Aug - 30 Sep30-day evaluation · iterate fixes · success metrics3Q4 success · Q5 PDPA
3.11 Oct - 14 OctM3 Clinic Locator · GPS routing · digital referralM34
3.215 Oct - 28 OctM6 Adverse Reaction Loop · cross-PA broadcastM63
3.329 Oct - 11 NovM8 Cross-Clinic Continuity · multi-tenant dataM84
Onboard 3-512 Nov - 23 DecOnboard 3-5 group klinik · network effect4 (BD + Eng)
Hi-End upgrade24 Dec - 6 JanMid → Hi-End server · 4× H100 deployment2 (DevOps)
MOH audit prep7 Jan - 28 FebCompliance docs · external pen-test · MOH walkthroughM93 + compliance consultantQ6 production cert
Production live1 Mar 2027Steady-state · onboard 10+ klinik5 (steady-state)

4. 🎯 Milestones

DateMilestonePhaseOwnerCritical Path?
26 Apr 2026Doc Zam approval · medieco.alesa.my LIVEP0Founder
3 May 2026Module specs detail (M1/M4/M9) · 6 skeleton stubsP0Founder + EngYES
10 May 2026Q1 Preflight gate · Repo + CI/CD + staging LIVEP0→P1Eng LeadYES
24 May 2026Sprint 1.1 demo · M9 audit + auth + Patient modelP1Eng TeamYES
7 Jun 2026Sprint 1.2 demo · M1 Patient PA UI + triage flowP1Eng TeamYES
21 Jun 2026Sprint 1.3 demo · M4 Doctor PA · MVP COMPLETEP1Eng TeamYES
28 Jun 2026Q2/Q3 gates · Doc Zam clinical sign-off MVPP1→P2Doc Zam + FounderYES
5 Jul 2026Sprint 2.1 · M2 + M5 readyP2Eng Team
19 Jul 2026Sprint 2.2 · M7 ready · integration doneP2Eng Team
2 Aug 2026Klinik pilot deployment · UAT completeP2Eng + KlinikYES
16 Aug 2026Pilot soft launch (closed beta · staff family)P2All
25 Aug 2026Pilot 30-day mark · interim metricsP2All
30 Sep 2026Q4/Q5 gates · pilot success evalP2→P3Doc Zam + FounderYES
14 Oct 2026Sprint 3.1 · M3 deployedP3Eng
28 Oct 2026Sprint 3.2 · M6 deployedP3Eng
11 Nov 2026Sprint 3.3 · M8 deployed · network effect readyP3Eng
23 Dec 20265 group klinik onboardedP3BD + Eng
6 Jan 2027Hi-End server upgrade completeP3DevOps
28 Feb 2027MOH audit complete · external pen-test passedP3ComplianceYES
1 Mar 2027Q6 production certification · GO LIVEP3 EXITAllYES

5. 🔥 Critical Path

Activities yang kalau slip = whole project slip. Dah identified 8 critical milestones.

26 Apr ─────► 3 May ─────► 10 May ─────► 24 May ─────► 7 Jun ─────► 21 Jun ─────► 28 Jun
[approval]    [specs]       [Q1+repo]      [M9 done]      [M1 done]      [M4 done]      [Q2/Q3 sign-off]
   │              │              │              │              │              │              │
   │              │              │              │              │              │              ▼
   │              │              │              │              │              │           2 Aug
   │              │              │              │              │              │           [pilot live]
   │              │              │              │              │              │              │
   │              │              │              │              │              │              ▼
   │              │              │              │              │              │           30 Sep
   │              │              │              │              │              │           [Q4/Q5]
   │              │              │              │              │              │              │
   │              │              │              │              │              │              ▼
   │              │              │              │              │              │           28 Feb 27
   │              │              │              │              │              │           [MOH audit]
   │              │              │              │              │              │              │
   │              │              │              │              │              │              ▼
   │              │              │              │              │              │           1 Mar 27
   │              │              │              │              │              │           [GO LIVE]

CRITICAL PATH: 309 hari (26 Apr 2026 → 1 Mar 2027)
Slack on non-critical (P3 modul · onboarding cadence): ~30-45 hari boleh delay tanpa affect launch
⚠️ Critical risk to schedule:
  • Sprint 1.3 (M4 Doctor PA) — most complex · Doc Zam clinical review intensive · slip = whole MVP slip
  • Pilot deployment (Aug 2) — depends on klinik agreement signed by Jun 2026 · external dependency
  • MOH audit (Feb 2027) — external timeline · 4-week buffer included

6. 🔗 Sprint Dependencies

P0 Foundation ──► 1.1 (M9) ──► 1.2 (M1) ──► 1.3 (M4) ──► [Q2/Q3] ──► Pilot prep
                       │            │            │
                       │            │            └──► (uses M9 audit + Patient model)
                       │            └──► (uses M9 audit + Patient model)
                       └──► (no deps · foundation)

[Q2/Q3 sign-off] ──► 2.1 (M2 + M5) ──► 2.2 (M7) ──► Pilot prep ──► Pilot run ──► [Q4/Q5]
                          │              │
                          │              └──► (uses M4 RX dispatch · M1 queue · billing)
                          └──► (M2 needs M1+M4 · M5 needs M4 RX)

[Q4/Q5 sign-off] ──► 3.1 (M3) ──► 3.2 (M6) ──► 3.3 (M8) ──► Onboard ──► Hi-End upgrade ──► MOH audit ──► [Q6 GO LIVE]
                       │             │            │
                       │             │            └──► (M8 needs M1+M9 multi-tenant)
                       │             └──► (M6 needs M1+M5)
                       └──► (M3 standalone)

PARALLEL OPPORTUNITIES:
- 2.1: M2 + M5 boleh kerja parallel (no inter-dep)
- 3.1+3.2+3.3: kalau cukup capacity, boleh overlap (M3 standalone, M6 + M8 separate concerns)

7. 👥 Resource Allocation

SprintBE DevFE DevPrompt EngDevOpsQADoc ZamTotal FTE
P0 Foundation0.50.50.50.52.0
1.1 M9310.50.50.55.5
1.2 M12110.50.516.0
1.3 M42110.50.527.0
2.1 M2+M53110.50.517.0
2.2 M7310.50.50.50.56.0
Pilot run211127.0
3.1-3.3 (avg)2.510.50.50.50.55.5
Onboarding1110.53.5
MOH audit prep110.513.5
Peak headcount needed: Sprint 1.3 + Sprint 2.1 (~7 FTE incl Doc Zam intensive). Plan hire pipeline: Eng Lead by 26 Apr (already), 2 BE by 11 May, 1 FE + 1 prompt by 25 May.

8. 📈 Velocity Tracking

  • Story point Fibonacci: 1 (trivial) · 2 · 3 · 5 (typical task) · 8 · 13 (epic — break down)
  • Target velocity per sprint per FTE: ~13 SP (after 2 sprints calibration)
  • Sprint 1.1 forecast: 4 FTE × 13 SP = 52 SP; M9 epic estimated 50 SP
  • Sprint 1.2 forecast: 4 FTE × 13 SP = 52 SP; M1 epic estimated 55 SP (slight overrun risk · scope-trim plan ready)
  • Sprint 1.3 forecast: 4 FTE × 13 SP = 52 SP; M4 epic estimated 65 SP (REQUIRES SCOPE-TRIM atau overflow ke 2.1)
  • Burndown chart: Updated daily · visible Filament dashboard · alert if <30% remaining at Day 9
  • Retrospective adjustments: Sprint length boleh extend ke 3 weeks kalau velocity calibration off · NO SACRIFICE quality untuk speed

9. 🛡️ Schedule Contingency

ScenarioTriggerResponseSchedule Impact
M4 sprint overrunDay 9 burn <30% remainingTrim FR-4.13 (patient instr PDF) + FR-4.14 (referral) ke Sprint 2.10 days · scope-protect
Klinik pilot delayKlinik partner LOI not signed by 1 JunActivate Backup Klinik B · ALESA bear extra setup cost · slip pilot 2 weeks+14 days
GPU lead time slipL40S delivery >6 weeksCloud burst (gpt-4o-mini) until hardware arrives · pilot still go0 days · cost +RM 15K
Doc Zam unavailable Q3 reviewPersonal/professional conflictReschedule clinical review window · delay sign-off+7 days
Critical safety bug post-Q3Test fail clinical pathwayHot-fix sprint inserted · pilot delay until verified+14 to +28 days
Pilot data shows skill decayJunior doc over-rely AIActivate "blind mode" toggle · training intervention0 days
MOH audit prep slipCompliance gap detected lateExternal compliance consultant engaged · prep extended+30 days · cost +RM 30K
Total schedule buffer built-in: P0 (extra week) + P2 (1 month iteration) + P3 (4 weeks audit) = ~10 weeks contingency before launch slip.